Report claimed major disaster could ’endanger lives and interrupt the functioning of democracy in the UK

Parliamentary officials have insisted the Palace of Westminster is safe after being warned that a “catastrophe” could occur if restoration works are further delayed.
Clerks of both Houses of Parliaments said a “wide array of mitigations” was in place to manage risks at the crumbling grade I-listed building ahead of a planned restoration and renewal programme which could see all MPs moved out of the building for decades.
In a report published earlier this month, the cross-party public accounts committee (PAC) urged parliamentary authorities to “imagine the blow suffered by the UK’s morale and reputation” in the event of a major disaster in the building.
“At worst, a catastrophic event could occur [to the palace] that endangers lives and interrupts the functioning of democracy in the UK,” the report said.
In their interim response to the report, published yesterday, the two clerks of the Houses of Parliament accepted that only a full restoration programme could resolve “significant legacy issues” but claimed the building was “currently a safe place to work and visit”.
The PAC has reported at least 36 fire incidents in the palace in the last 10 years, 19 incidents of falling masonry, 12 asbestos incidents and repeated issues with leaking roofs and plumbing failures.
The committee said last month that every year of delay to refurbishment works will cost taxpayers £420m with a delay on a vote on how to proceed, which had been expected before Easter, already costing nearly £300m.
MPs are expected to take a final decision on the way forward in 2030, either a ‘full decant’ costing up to £15.6bn and taking up to 24 years, which will see both Houses of Parliament move out of the building for the majority of the works, or an ‘enhanced maintenance and improvement plus’ option during which only the House of Lords would move out, costing up to £39.2bn and taking up to 61 years.
The projected price tags and timescales of the two options have caused alarm in Westminster with parliamentary authorities stating yesterday that there was a need to “bear down” on cost and schedule estimates before the 2030 vote.
Detailed plans for a first phase of works, including estimated cost ranges, are due to be presented to the restoration and renewal programme board by March 2027.